Rates (Northern Ireland) Order 1977

[F12.(1) A completion notice shall—N.I.

(a)specify the building to which it relates; and

(b)state the day which the Department proposes as the completion day in relation to the building.

(2) Where at the time a completion notice is served it appears to the Department that the building to which the notice relates is not completed, the Department shall propose as the completion day such day, not later than 3 months from the day on which the notice is served, as the Department considers is a day by which the building can reasonably be expected to be completed.

(3) Where at the time a completion notice is served it appears to the Department that the building to which the notice relates has been completed, the Department shall propose as the completion day the day on which the notice is served.]