Changes over time for: Section 56

 Help about opening options

Alternative versions:

Status:

This version of this provision is prospective. Help about Status

Close

Status

The term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section. A version of a provision is prospective either:

  1. where the provision (Part, Chapter or section) has never come into force or;
  2. where the text of the provision is subject to change, but no date has yet been appointed by the appropriate person or body for those changes to come into force.

Commencement Orders listed in the ‘Changes to Legislation’ box as not yet applied may bring this prospective version into force.

Changes to legislation:

There are currently no known outstanding effects for the Heat Networks (Scotland) Act 2021, Section 56. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Prospective

56Requirement for heat network zone permitS

This section has no associated Explanatory Notes

(1)The permit authority may by notice prohibit the operation of a heat network in such heat network zone as may be designated in the notice unless a heat network zone permit for the heat network zone is held by—

(a)the person operating the heat network, or

(b)the person on whose behalf the heat network is operated.

(2)But a notice under subsection (1) designating a heat network zone may not require a person who is entitled to operate a heat network in the heat network zone immediately before the day on which the notice takes effect to hold a heat network zone permit for the heat network zone in order to—

(a)operate the heat network, or

(b)permit another person to operate the heat network on their behalf.

(3)For the purposes of subsection (2), a person is entitled to operate a heat network if at that time the person—

(a)holds a heat network consent in relation to the operation of the heat network, or

(b)is exempt from the requirement to hold a heat network consent in relation to the operation of the heat network by virtue of regulations under section 19(1).

(4)But the permit authority may not issue a notice under subsection (1)—

(a)in such circumstances as may be specified,

(b)if any specified procedure has not been complied with.

(5)The permit authority may revoke a notice issued under subsection (1).

(6)But the permit authority may not revoke a notice issued under subsection (1)—

(a)in such circumstances as may be specified,

(b)if any specified procedure has not been complied with.

(7)The permit authority must—

(a)publish a notice issued under subsection (1), and

(b)give notice of the revocation of a notice issued under subsection (1),

in such form and manner as may be specified.

(8)In this section, “specified” means specified in regulations made by the Scottish Ministers.

(9)In this Part, a “heat network zone permit” is a permit issued by the permit authority.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources