xmlns:atom="http://www.w3.org/2005/Atom"

PART 2Cremation

Crematorium: further requirements

59New crematorium: notice

(1)This section applies where a person proposes to establish a crematorium.

(2)The person must give an inspector of cremation notice of the day on which the person proposes to determine the first application made under section 48(1) for a cremation to be carried out in the crematorium (the “first application”).

(3)Notice under subsection (2)—

(a)must be given at least 3 months before the day on which the person proposes to determine the first application, and

(b)must be in writing.

(4)The person may not determine the first application unless—

(a)an inspector of cremation has given notice in writing to the person that the person may determine the first application on or after a day specified in the notice, and

(b)the determination is made on or after that day.