Reservoirs (Scotland) Act 2011

71SEPA’s power to arrange taking of safety and other measures
This section has no associated Explanatory Notes

(1)This section applies where SEPA has by notice under section 69(2) required a reservoir manager to take a measure and the reservoir manager has failed to do so.

(2)SEPA may arrange for the taking of the measure under the supervision of an engineer appointed by it under this section.

(3)Where the engineer is satisfied that the measure has been taken, the engineer must give a certificate to that effect to SEPA.

(4)The reservoir manager must pay SEPA the amount of any expenses reasonably incurred by it in making arrangements under this section.