Part 2Dispute resolution
Effect of failure to comply with property factor enforcement order
I123Effect of failure to comply with property factor enforcement order
1
2
3
The F5First-tier Tribunal may not decide that a property factor has failed to comply with a property factor enforcement order––
a
unless the period within which the order requires any work to be executed has ended, or
b
if the F6First-tier Tribunal is satisfied, on the submission of the property factor or otherwise––
i
that the property factor is unable to comply with the order because of a lack of necessary rights (of access or otherwise) despite having taken reasonable steps for the purposes of acquiring those rights, or
ii
that any action required by the order is likely to endanger any person.
4
Where the F7First-tier Tribunal is prevented by reason only of subsection (3)(b) from deciding that a property factor has failed to comply with a property factor enforcement order, the F8First-tier Tribunal must serve notice on the Scottish Ministers stating that F9it considers the property factor to be unable to comply with the property factor enforcement order.