Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
SCHEDULE 11SListed buildings: authorised works
(introduced by section 63(5))
This schedule has no associated Explanatory Notes
Listed Building | Sheet of Parliamentary plans | Authorised works |
---|
Port Edgar Barracks | W12 | Any survey or building works necessary to mitigate potential impacts due to vibration, dust and construction, including placement or attachment of monitoring equipment. To include the construction of a temporary bridge and access road, removal of same and subsequent re-instatement of land within the boundary of the complex following construction works. |
St Margaret's Hope, former Admiralty House | W13 and W14 | Any survey or building works necessary to mitigate potential impacts due to vibration or dust, including placement or attachment of monitoring equipment. |
St Margaret's Hope, Arch | W13 and W14 | Dismantling and relocation, including any necessary alteration, to a location to be determined by Ministers. |
Inchgarvie House, South Queensferry | W12 | Any survey or building works necessary to mitigate potential impacts due to vibration or dust, including placement or attachment of monitoring equipment. |