(1)Not less than 3 years before the beginning of the period to which a flood risk management plan is to relate, SEPA must publish a statement setting out—
(a)the steps under this section, and any other consultation measures, which it is to take in connection with the preparation of the plan, and
(b)the dates on or by which those steps and measures are to be taken.
(2)Not less than one year before the beginning of the period to which a flood risk management plan is to relate, SEPA must publish a draft of the plan.
(3)Publication of a statement under subsection (1) and a draft under subsection (2) is to be in such manner as SEPA considers appropriate.
(4)On publishing a statement or draft plan SEPA must—
(a)publicise—
(i)that fact, and
(ii)the opportunity to make representations about the statement or draft plan under subsection (6),
(b)make copies of the statement or draft plan available for public inspection for such period, which must be at least 3 months beginning with the date of its publication, as SEPA may determine,
(c)consult the persons specified in subsection (5), and
(d)take such steps as it considers appropriate for the purpose of encouraging those persons to participate appropriately in the preparation of the plan.
(5)The persons referred to in subsection (4)(c) are—
(a)every responsible authority which has functions exercisable in or in relation to the flood risk management district to which the plan relates (“the district”),
(b)every category 1 responder (other than a responder which is a responsible authority) which has functions exercisable in or in relation to the district,
(c)Scottish Natural Heritage,
(d)where any part of the district has been designated as a National Park, the National Park authority for the National Park, and
(e)such other persons as SEPA considers appropriate.
(6)Any person who wishes to make representations to SEPA about a statement or draft plan may do so before the expiry of the period determined under subsection (4)(b).
(7)In preparing the draft flood risk management plan SEPA must take into account—
(a)any views on the statement relating to the plan expressed by those consulted under subsection (4)(c), and
(b)any representations about the statement,
which are received by SEPA before the expiry of the period determined under subsection (4)(b).
(8)In preparing the flood risk management plan for submission to the Scottish Ministers SEPA must take into account—
(a)any views on the draft plan expressed by those consulted under subsection (4)(c), and
(b)any representations about the draft plan,
which are received by SEPA before the expiry of the period determined under subsection (4)(b).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: