Flood Risk Management (Scotland) Act 2009

10Flood risk assessments: reviewS

This section has no associated Explanatory Notes

(1)SEPA must—

(a)by 22nd December 2018 or such earlier date as the Scottish Ministers may direct (“the operative date”), review and where appropriate update each flood risk assessment prepared under section 9, and

(b)by the end of the period of 6 years beginning with the operative date, and of each subsequent period of 6 years, review and where appropriate update the latest flood risk assessment updated after review under this section.

(2)Section 9(3) to (5) applies in relation to the review and updating of a flood risk assessment.

Commencement Information

I1S. 10 in force at 26.11.2009 by S.S.I. 2009/393, art. 2, Sch.