xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULE 1SMatters to be included in flood risk management plans

Part 1 SMatters to be included in every plan

8SA summary of—

(a)the steps taken under subsections (2) to (5) of section 30 in relation to the plan,

(b)any other consultation measures taken in connection with the preparation of the plan (including those taken in connection with the flood risk assessment mentioned in paragraph 2 and the maps mentioned in paragraph 3), and

(c)changes made to the plan in light of the views and representations received on it.

Commencement Information

I1Sch. 1 para. 8 in force at 26.11.2009 by S.S.I. 2009/393, art. 2, Sch.