Part 4 SFlood risk management: local authority functions

Valid from 24/12/2010

General powerS

56General power to manage flood riskS

(1)A local authority may do anything which it considers—

(a)will contribute to the implementation of current measures described in any relevant local flood risk management plan,

(b)is necessary to reduce the risk of a flood in its area which is likely to—

(i)occur imminently, and

(ii)have serious adverse consequences for human health, the environment, cultural heritage or economic activity, or

(c)will otherwise manage flood risk in its area without affecting the implementation of the measures mentioned in paragraph (a).

(2)Without prejudice to the generality of subsection (1), a local authority may in particular—

(a)carry out any operations to which a flood protection scheme relates (see section 60),

(b)carry out any other flood protection work,

(c)carry out any temporary works required for the purposes of a flood protection scheme or any other flood protection work,

(d)enter into agreements or arrangements with any other person—

(i)for the carrying out by that person or by the authority of any work which could be done by the authority under this Part, or

(ii)relating to the management by that person of land in a way which can assist in the retention of flood water or slowing the flow of such water,

(e)make contributions towards expenditure incurred by any other person doing something which could be done by the authority under this Part,

(f)(make payments to any other person in compensation for income lost as a result of entering into agreements or arrangements of the type mentioned in paragraph (d)(ii), and

(g)receive from any other person contributions towards expenditure incurred by the authority in exercising any of its functions under this Part.

(3)Work carried out under this section may be carried out within or outwith the local authority's area.

57Limits of general powerS

(1)The power under section 56 does not enable a local authority to do anything which it is, by virtue of a limiting provision, unable to do.

(2)In subsection (1), a “limiting provision” is one which—

(a)prohibits or prevents the local authority from doing anything or limits its powers in that respect, and

(b)is expressed in an enactment (whenever passed or made).

(3)The absence from an enactment of provision conferring any power does not of itself make that enactment a limiting provision.

58Limits of general power: statutory undertakingsS

(1)A local authority may not exercise the power under section 56 in a way which—

(a)damages any works or property belonging to a statutory undertaker, or

(b)interferes with the carrying on of its statutory undertaking,

unless the undertaker consents.

(2)But consent is not required if it is withheld unreasonably.

(3)It is for the Scottish Ministers to determine any question which arises as to whether consent has been withheld unreasonably, and their decision is final.

Valid from 01/06/2011

Valid from 29/11/2010

Flood protection schemesS

60Flood protection schemesS

(1)A flood protection scheme is a scheme by a local authority for the management of flood risk within the authority's area.

(2)A proposed flood protection scheme must—

(a)contain a description of the operations the local authority proposes to carry out,

(b)include such maps, plans and specifications as may be specified by regulations by the Scottish Ministers,

(c)state how the operations will contribute to the implementation of current measures described in any relevant local flood risk management plan, and

(d)inasmuch as they will not so contribute, state the reasons why the local authority considers carrying them out will not affect the implementation of those measures.

(3)Schedule 2 makes further provision about the making of flood protection schemes.

(4)The Scottish Ministers may by order amend schedule 2 so as to modify the procedure for making flood protection schemes.

(5)Before making an order under subsection (4), the Scottish Ministers must consult—

(a)every local authority,

(b)such bodies appearing to them to be representative of the interests of local authorities as they consider appropriate,

(c)SEPA,

(d)Scottish Natural Heritage,

(e)Scottish Water,

(f)the National Park authority for each National Park, and

(g)such other persons as they consider appropriate.

Valid from 24/12/2010

61Orders under the Land Drainage (Scotland) Act 1958S

(1)This section applies where an improvement order affects any land on which operations are proposed to be carried out under a flood protection scheme.

(2)The flood protection scheme may include proposals to—

(a)vary the improvement order by—

(i)removing land from the improvement area,

(ii)removing or rendering ineffective all or any part of the drainage or protective works specified in the improvement order, or

(iii)amending, reapportioning or removing any obligations of maintenance imposed on the authorised persons under the improvement order, or

(b)revoke the improvement order.

(3)But the scheme may not include proposals to vary the improvement order so as to impose any new obligations on the authorised persons in respect of operations described in the scheme.

(4)Where the proposed operations will materially alter drainage works or protective works, the scheme must include proposals to vary the improvement order so as to remove the obligation of maintenance in respect of the part of the drainage works or protective works so altered.

(5)On commencement of the flood protection scheme, the improvement order is varied or, as the case may be, revoked to the extent specified in the scheme.

(6)Where an improvement order has been varied or revoked by a flood protection scheme, the local authority must cause a notice of the variation or revocation to be registered in the Land Register of Scotland or recorded in the Register of Sasines (as applicable).

(7)The Scottish Ministers may by order specify the form and content of a notice under subsection (6).

(8)In this section—

  • authorised persons” has the meaning given in section 2(2) of the Land Drainage (Scotland) Act 1958 (c. 24),

  • drainage works” has the meaning given in section 18(1) of that Act,

  • improvement area” has the meaning given in section 1(3) of that Act,

  • improvement order” has the meaning given in section 1(1) of that Act,

  • protective works” has the meaning given in section 2(1)(d) of that Act.

Prospective

62Registers of flood protection schemesS

(1)Every local authority must keep a register of flood protection schemes.

(2)A local authority must enter into its register—

(a)details of each relevant scheme including—

(i)a summary of the operations described in the scheme,

(ii)a description (by reference to a map) of the land affected by those operations, and

(iii)a note of the date on which notice of the scheme is first published under paragraph 1(1)(a) of schedule 2,

(b)a note of the following in relation to each such scheme—

(i)any decision made under paragraph 4(1), 5(1), 7(4), or 9(1) of schedule 2,

(ii)the fact that notice has been given to the Scottish Ministers under paragraph 5(5) of that schedule including whether any relevant objector is a local authority or a National Park authority,

(iii)the fact that notice has been given of proposed modifications under paragraph 7(5)(a) or 9(3)(a) of that schedule,

(c)where such a scheme is confirmed with modifications, the information specified in paragraph (a)(i) and (ii) in relation to the modified scheme, and

(d)a note of any suspension of the operation of such a scheme under paragraph 12(6) of schedule 2.

(3)For the purposes of subsection (2)(a), a relevant scheme is a scheme—

(a)proposed by the local authority, or

(b)in relation to which it is notified under paragraph 1(1)(f)(iii) of schedule 2.

(4)A local authority may remove information from its register relating to a scheme if the scheme is rejected under paragraph 4(1)(b), 7(4)(c) or 9(1)(c) of schedule 2.

(5)A local authority must amend its register to reflect any decision of a sheriff under paragraph 12(7) of schedule 2 to quash a scheme recorded in its register in whole or in part.

(6)Where a local authority enters information in its register about a scheme in relation to which it notified another local authority under paragraph 1(1)(f)(iii) of schedule 2, it must notify that authority of the information entered.

(7)A local authority must make available its register for public inspection and may charge a reasonable fee for doing so.

Valid from 24/12/2010

Valid from 24/12/2010

GeneralS

71Interpretation of Part 4S

In this Part—

  • relevant local flood risk management plan” means, in relation to a local authority, a local flood risk management plan for a local plan district that includes all or part of the local authority's area,

  • scheme documents” means, in relation to a proposed flood protection scheme, the documents containing the material specified in, or by regulations made under, section 60(2),

  • statutory undertaker” means—

    (a)

    the holder of a licence under section 6(1) of the Electricity Act 1989 (c. 29),

    (b)

    a gas transporter within the meaning of Part 1 of the Gas Act 1986 (c. 44),

    (c)

    the Civil Aviation Authority,

    (d)

    a holder of a licence under Chapter 1 of the Transport Act 2000 (c. 38),

    (e)

    the operator of an electronic communications code network within the meaning of paragraph 1(1) of Schedule 17 to the Communications Act 2003 (c. 21), and

    (f)

    any other person who is a statutory undertaker within the meaning of section 214(1) of the Town and Country Planning (Scotland) Act 1997 (c. 8),

  • “statutory undertaking”—

    (a)

    means, in relation to a person mentioned in paragraphs (a) to (e) in the definition of “statutory undertaker”, the person's undertaking,

    (b)

    means, in relation to Scottish Water, its core functions within the meaning of section 70(2) of the Water Industry (Scotland) Act 2002 (asp 3),

    (c)

    otherwise has the meaning given in the Town and Country Planning (Scotland) Act 1997.