(1)The Scottish Ministers must prepare and publish a plan for—
(a)promoting energy efficiency; and
(b)improving the energy efficiency of living accommodation,
in Scotland.
(2)The plan must set annual energy efficiency targets and describe how those targets are to be reported on.
(3)The plan must also include details of how the Scottish Ministers intend to update planning and building regulations to ensure that all new buildings avoid a specified and rising proportion of the projected greenhouse gas emissions from their use, calculated on the basis of the approved design and plans for the specific building, through the installation and operation of low and zero-carbon generating technologies.
(4)The plan prepared under subsection (1) must be published no later than 12 months after the day on which this section comes into force.
(5)The Scottish Ministers—
(a)may, from time to time; and
(b)must, before the end of the period mentioned in subsection (6),
review the plan prepared and published under this section.
(6)The period referred to in subsection (5)(b) is the period of 3 years beginning with the day on which—
(a)the plan is first published; or
(b)the plan was last reviewed under subsection (5).
(7)Where, following a review under subsection (5), the Scottish Ministers vary the plan, they must, as soon as reasonably practicable after so doing, publish the plan as so varied.
(8)In preparing or varying the plan, the Scottish Ministers must have regard to the contributions which improvements to buildings and changes in building standards can make to the delivery of energy efficiency and to the reduction of greenhouse gas emissions.
(9)In this section—
“energy efficiency” includes the use of—
technologies (other than those used for the production of heat) reliant on renewable sources of energy;
materials and equipment the manufacture or use of which produces or involves lower emissions of greenhouse gases than other materials and equipment; and
surplus heat from electricity generation or other industrial processes for district heating or other purposes;
“fossil fuel” means—
coal;
lignite;
peat;
natural gas (within the meaning of the Energy Act 1976 (c. 76));
crude liquid petroleum;
petroleum products (within the meaning of that Act);
any substance produced directly or indirectly from a substance mentioned in paragraphs (a) to (f);
“renewable sources” means sources other than fossil fuel and nuclear fuel.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Text created by the Scottish Government to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Acts of the Scottish Parliament except those which result from Budget Bills.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: