Prospective

PART 6E+WOBLIGATIONS RELATING TO DEVELOPMENT AND USE OF LAND

CHAPTER 1E+WPLANNING OBLIGATIONS

169Legal challenges relating to applications made to the Welsh Ministers or Secretary of StateE+W

(1)This section applies where an application has been made to the Welsh Ministers or the Secretary of State under section 167(3).

(2)A court may entertain proceedings for questioning a determination by the Welsh Ministers or the Secretary of State that the planning obligation is to continue to have effect without modification only if—

(a)the proceedings are brought by a claim for judicial review, and

(b)the claim form is filed before the end of 6 weeks beginning with the day after the day notice of the determination is given under section 167(7).

(3)A court may entertain proceedings for questioning a failure by the Welsh Ministers or the Secretary of State to give notice in accordance with section 167(7) only if—

(a)the proceedings are brought by a claim for judicial review, and

(b)the claim form is filed before the end of 6 weeks beginning with the day after the day the period specified under section 167(7) ends.

Commencement Information

I1S. 169 not in force at Royal Assent, see s. 409(2)