PART 2E+WTHE OFFICE OF ENVIRONMENTAL GOVERNANCE WALES

Prospective

Improvement reports and improvement plansE+W

23Improvement reports: contentE+W

(1)An improvement report must—

(a)set out the details of the alleged failure to—

(i)comply with environmental law,

(ii)implement or apply environmental law effectively, or

(iii)make effective environmental law;

(b)explain the OEGW’s reasons for considering that there has been such a failure;

(c)set out the impact or possible impact of the failure;

(d)recommend actions for the Welsh Ministers to take in response to the failure;

(e)propose timescales for taking those actions.

(2)The actions recommended for the Welsh Ministers under subsection (1)(d) may not include—

(a)revoking or varying an administrative decision taken by a public authority in relation to a particular person or case, or

(b)requiring another public authority to revoke or vary such a decision.

Commencement Information

I1S. 23 in force at 27.4.2028 (conditional on an earlier day not being appointed by Welsh Ministers), see s. 46(4)(5)(6)(c)