(1)This section applies where—
(a)an activity specified in a temporary stop notice is, at the time the notice takes effect, authorised by an infrastructure consent order granted before the day the notice takes effect, or
(b)a relevant planning authority withdraws a temporary stop notice after it has taken effect.
(2)This section does not apply by virtue of subsection (1)(b) where—
(a)an activity specified in the temporary stop notice is authorised by an infrastructure consent order granted on or after the day the notice takes effect, or
(b)the planning authority withdraws the notice after the grant of that consent.
(3)Any person who has an interest in the land to which the notice relates on the day the notice takes effect is entitled, on making a claim to the relevant planning authority, to be paid compensation by the authority for any loss or damage suffered by the person that is directly attributable to the effect of the notice.
(4)The loss or damage for which compensation is payable includes any amount payable by the claimant in respect of a breach of contract caused by taking action necessary to comply with the notice.
(5)No compensation is payable under this section in respect of the prohibition of an activity which, at any time when the temporary stop notice has effect, constitutes or contributes to an offence under section 103 or 104.
(6)No compensation is payable under this section for loss or damage that the claimant could have avoided by—
(a)providing information that the claimant was required to provide by a notice served by the planning authority under section 111 of this Act or section 16 of the Local Government (Miscellaneous Provisions) Act 1976 (c. 57), or
(b)co-operating with the planning authority in any other way when responding to the notice.
(7)A claim for compensation under this section must be made in writing within 12 months beginning—
(a)in a case falling within subsection (1)(a) but not within subsection (1)(b), with the day the temporary stop notice takes effect;
(b)in a case falling within subsection (1)(b), with the day the notice is withdrawn.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: