Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
(introduced by section 63)
1E+WThe acquisition of land, compulsorily or by agreement.
Commencement Information
I1Sch. 1 para. 1 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I2Sch. 1 para. 1 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(K)
2E+WThe creation, suspension or extinguishment of, or interference with, interests in or rights over land (including navigation over water), compulsorily or by agreement.
Commencement Information
I3Sch. 1 para. 2 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I4Sch. 1 para. 2 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
3E+WThe abrogation or modification of agreements relating to land.
Commencement Information
I5Sch. 1 para. 3 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I6Sch. 1 para. 3 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
4E+WCarrying out specified excavation, mining, quarrying or boring operations in a specified area.
Commencement Information
I7Sch. 1 para. 4 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I8Sch. 1 para. 4 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
5E+WThe operation of a generating station.
Commencement Information
I9Sch. 1 para. 5 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I10Sch. 1 para. 5 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
6E+WKeeping electric lines installed above ground.
Commencement Information
I11Sch. 1 para. 6 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I12Sch. 1 para. 6 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
7E+WThe protection of the property or interests of any person.
Commencement Information
I13Sch. 1 para. 7 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I14Sch. 1 para. 7 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
8E+WThe imposition or exclusion of obligations or liability in respect of acts or omissions.
Commencement Information
I15Sch. 1 para. 8 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I16Sch. 1 para. 8 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
9E+WCarrying out surveys or taking soil samples.
Commencement Information
I17Sch. 1 para. 9 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I18Sch. 1 para. 9 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
10E+WCutting down, uprooting, topping or lopping trees or shrubs or cutting back their roots.
Commencement Information
I19Sch. 1 para. 10 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I20Sch. 1 para. 10 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
11E+WThe removal, disposal or re-siting of apparatus.
Commencement Information
I21Sch. 1 para. 11 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I22Sch. 1 para. 11 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
12E+WCarrying out civil engineering or other works.
Commencement Information
I23Sch. 1 para. 12 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I24Sch. 1 para. 12 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
13E+WThe diversion of navigable or non-navigable watercourses.
Commencement Information
I25Sch. 1 para. 13 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I26Sch. 1 para. 13 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
14E+WThe stopping up or diversion of highways.
Commencement Information
I27Sch. 1 para. 14 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I28Sch. 1 para. 14 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
15E+WCharging tolls, fares (including penalty fares) and other charges.
Commencement Information
I29Sch. 1 para. 15 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I30Sch. 1 para. 15 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
16E+WThe designation of a highway as a trunk road or special road.
Commencement Information
I31Sch. 1 para. 16 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I32Sch. 1 para. 16 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
17E+WThe specification of the classes of traffic authorised to use a highway.
Commencement Information
I33Sch. 1 para. 17 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I34Sch. 1 para. 17 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
18E+WThe appropriation of a highway for which the person proposing to construct or improve a highway is the highway authority.
Commencement Information
I35Sch. 1 para. 18 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I36Sch. 1 para. 18 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
19E+WThe transfer to the person proposing to construct or improve a highway of a highway for which that person is not the highway authority.
Commencement Information
I37Sch. 1 para. 19 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I38Sch. 1 para. 19 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
20E+WThe specification of the highway authority for a highway.
Commencement Information
I39Sch. 1 para. 20 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I40Sch. 1 para. 20 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
21E+WThe operation and maintenance of a transport system.
Commencement Information
I41Sch. 1 para. 21 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I42Sch. 1 para. 21 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
22E+WEntering into an agreement for the provision of police services.
Commencement Information
I43Sch. 1 para. 22 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I44Sch. 1 para. 22 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
23E+WThe discharge of water into inland waters or underground strata.
Commencement Information
I45Sch. 1 para. 23 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I46Sch. 1 para. 23 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
24E+WDeeming a marine licence under Part 4 of the Marine and Coastal Access Act 2009 (c. 23) to have been given by the Welsh Ministers for activities specified in the order and subject to such conditions as may be specified in the order.
Commencement Information
I47Sch. 1 para. 24 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I48Sch. 1 para. 24 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
25E+WDeeming any such conditions to have been attached to the marine licence by the Welsh Ministers under that Part.
Commencement Information
I49Sch. 1 para. 25 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I50Sch. 1 para. 25 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
26E+WThe creation of a harbour authority.
Commencement Information
I51Sch. 1 para. 26 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I52Sch. 1 para. 26 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
27E+WChanging the powers and duties of a harbour authority.
Commencement Information
I53Sch. 1 para. 27 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I54Sch. 1 para. 27 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
28E+WThe making of byelaws by any person and their enforcement.
Commencement Information
I55Sch. 1 para. 28 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I56Sch. 1 para. 28 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
29(1)The creation of offences within sub-paragraph (2) in connection with—E+W
(a)non-payment of tolls, fares or other charges,
(b)a person’s failure to give the person’s name or address in accordance with provision relating to penalty fares,
(c)enforcement of byelaws, or
(d)construction, improvement, maintenance or management of a harbour.
(2)An offence is within this sub-paragraph if—
(a)it is triable only summarily,
(b)a person guilty of the offence is not liable to imprisonment, and
(c)any fine to which a person guilty of the offence may be liable cannot be higher than level 3 on the standard scale.
Commencement Information
I57Sch. 1 para. 29 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I58Sch. 1 para. 29 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
30E+WThe transfer of property, rights, liabilities or functions.
Commencement Information
I59Sch. 1 para. 30 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I60Sch. 1 para. 30 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
31E+WThe transfer, leasing, suspension, discontinuance and revival of undertakings.
Commencement Information
I61Sch. 1 para. 31 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I62Sch. 1 para. 31 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
32E+WThe payment of contributions.
Commencement Information
I63Sch. 1 para. 32 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I64Sch. 1 para. 32 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
33E+WThe payment of compensation.
Commencement Information
I65Sch. 1 para. 33 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I66Sch. 1 para. 33 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
34E+WThe submission of disputes to arbitration.
Commencement Information
I67Sch. 1 para. 34 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I68Sch. 1 para. 34 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
35E+WThe alteration of borrowing limits.
Commencement Information
I69Sch. 1 para. 35 in force at 4.6.2024 for specified purposes, see s. 147(1)(b)
I70Sch. 1 para. 35 in force at 15.12.2025 in so far as not already in force by S.I. 2025/698, art. 3(k)
36(1)This paragraph applies for the purposes of this Schedule.E+W
(2)“Transport system” means any of the following—
(a)a railway;
(b)a tramway;
(c)a trolley vehicle system;
(d)a system using a mode of guided transport prescribed by order under section 2 of the Transport and Works Act 1992 (c. 42).
(3)“Maintenance”, in relation to a transport system, includes the inspection, repair, adjustment, alteration, removal, reconstruction or replacement of the system.
(4)The following terms have the meanings given by section 67(1) (interpretation) of the Transport and Works Act 1992 (c. 42)—
“guided transport” (“trafnidiaeth gyfeiriedig”);
“tramway” (“tramffordd”);
“trolley vehicle system” (“system cerbydau troli”).
Commencement Information
I71Sch. 1 para. 36 not in force at Royal Assent, see s. 147(2)
I72Sch. 1 para. 36 in force at 15.12.2025 by S.I. 2025/698, art. 3(k)
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: