Section 65 – Land to which authorisation of compulsory acquisition can relate

182.Section 65 provides that an infrastructure consent order may only include provision authorising the compulsory acquisition of land if the land is in Wales or the Welsh marine area and one of the following conditions is met:

  • the condition in subsection (2) is that the application for infrastructure consent included a request for compulsory acquisition of the land to be authorised;

  • the condition in subsection (3) is that all persons with an interest in the land consent to the inclusion of this provision;

  • the condition in subsection (4) is that the procedure specified in regulations has been followed in relation to that land.

183.Wales” and “Welsh marine area” are defined in section 143.

Back to top

Options/Help

Print Options

Close

Explanatory Notes

Text created by the Welsh Government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes accompany all Acts of Senedd Cymru.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources