Infrastructure (Wales) Act 2024

Section 33 – Deciding on the validity of an application and notifying the applicant

80.Section 33 requires the Welsh Ministers, on receiving an application for infrastructure consent, to decide whether or not to accept an application as valid.

81.An application must be considered valid if it is received within the period specified in regulations and complies with the requirements imposed by or under section 32. The Welsh Ministers must give notice to the applicant of a decision to accept the application as a valid application.

82.Where an application does not comply with the requirements in this section or section 32 and so cannot be accepted by the Welsh Ministers, they must notify the applicant of this decision, and give the reasons why it cannot be accepted as valid.

Back to top

Options/Help

Print Options

Close

Explanatory Notes

Text created by the Welsh Government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes accompany all Acts of Senedd Cymru.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources