Section 15 – Hazardous waste facilities
34.Section 15 specifies that the construction of a hazardous waste facility is a Significant Infrastructure Project if:
the facility is in Wales or the Welsh marine area,
the main purpose of the facility is the final disposal or recovery of hazardous waste, and
the facility is expected to have the capacity specified in subsection (2).
35.The section also specifies that the alteration of a hazardous waste facility is a Significant Infrastructure Project if:
the facility is in Wales or the Welsh marine area,
the main purpose of the facility is the final disposal or recovery of hazardous waste, and
the alteration is expected to increase the capacity of the facility as specified in subsection (3)(c).