Infrastructure (Wales) Act 2024 Explanatory Notes

Water

Section 12 – Dams and reservoirs

30.Section 12 specifies the circumstances when development relating to dams and reservoirs will be a Significant Infrastructure Project. These are:

  • the construction of a dam or reservoir in Wales if the volume of water to be held back by the dam or stored in the reservoir is expected to exceed 10 million cubic metres;

  • the alteration of a dam or reservoir in Wales if the additional volume of water to be held back by the dam or stored in the reservoir as a result of the alteration is expected to exceed 10 million cubic metres.

Section 13 – Transfer of water resources

31.Section 13 specifies that the transfer of water resources is a Significant Infrastructure Project when:

  • the development is carried out by one or more water undertakers,

  • the development takes place in Wales,

  • the volume of water to be transferred as a result of the development is expected to exceed 100 million cubic metres per year, and

  • the development enables the transfer of water resources, subject to limitations.

Back to top