Section 13 – Transfer of water resources
31.Section 13 specifies that the transfer of water resources is a Significant Infrastructure Project when:
the development is carried out by one or more water undertakers,
the development takes place in Wales,
the volume of water to be transferred as a result of the development is expected to exceed 100 million cubic metres per year, and
the development enables the transfer of water resources, subject to limitations.