Section 10 – Harbour facilities
24.Section 10 specifies the circumstances when the construction of a harbour facility is a Significant Infrastructure Project. These are:
the project will be wholly in Wales, the Welsh marine area or both,
the project will not be, or will not form part of, a reserved trust port, and
the project can handle the embarkation or disembarkation of at least the relevant quantity of material per year.
25.Alterations to a harbour facility will be a Significant Infrastructure Project when the effect of the alteration is expected to be to increase by at least the relevant quantity of material per year the quantity of material handled by the harbour.
26.Subsections (3) to (6) set out what “the relevant quantity” is.