Section 4 – Integrated network maps
15.Local authorities will have to prepare a second map, which will show the new and improved active travel routes and facilities that they consider are necessary for the purpose of developing or enhancing an integrated network. This will be a forward looking map which will show how the existing network could be advanced in future years. The period to which the map is to relate will be included in guidance to be given by the Welsh Ministers under section 4.
16.The same arrangements for Ministerial approval, revision of the maps and guidance will apply to the integrated network maps as apply to the existing routes maps. However, there will be no requirement for the submission of a statement and explanation, and the integrated network maps will be required to be resubmitted every three years.