Regulation 4

SCHEDULE 1FORM OF FIXED PENALTY NOTICE

Regulation 7

SCHEDULE 2AMOUNT OF PENALTY

TABLE

(1)(2)(3)(4)(5)
Item No.Offence under the 1991 ActBrief descriptionAmount of penaltyDiscounted amount
1.An offence under section 54(5).Failure to comply with duties under s.54 (advance notice of certain works, etc.).£120.£80.
2.An offence under section 55(5).Beginning to execute works in contravention of s.55 (notice of starting date).£120.£80.
3.An offence under section 55(9)(1).Failure to give notice in accordance with s.55(8) (notice to be given on s.55 notice ceasing to have effect).£120.£80.
4.An offence under section 57(4).Failure to give notice in accordance with s.57 (notice of emergency works).£120.£80.
5.An offence under section 70(6) consisting of a failure to comply with subsection (3) or (4A)(2).Failure to comply with requirements to give notice of completion of reinstatement.£120.£80.
6.An offence created by regulations made under section 74(7B).Failure to give a notice required by regulations under s.74 (charge for occupation of the highway where works unreasonably delayed).£120.£80.

Regulation 10

SCHEDULE 3FORM OF NOTICE WITHDRAWING A FIXED PENALTY NOTICE

(1)

Subsections (8) and (9) of section 55 are inserted by the Traffic Management Act 2004 (c. 18), section 49(2).

(2)

Section 70(3) is substituted and section 70(4A) inserted by the Traffic Management Act 2004 (c. 18), section 54(3).