8.—(1) For the purposes of section 54, an undertaker must give not less than three months' advance notice of major works, except where such works are —
(a)the subject of a notice under section 55(1) given in accordance with regulation 9(3) and in respect of which no notice has already been given under this paragraph; or
(b)notified under paragraph 2(1)(d) of Schedule 3A to the 1991 Act.
(2) For the purposes of section 54(4A), the period prescribed is 2 days beginning with the starting date specified in the notice.
(3) For the purposes of section 54(4B), the period prescribed is 15 days.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: