7.  The undertaker must—

(a)at all times afford reasonable facilities to the engineer for access to any relevant work during its construction; and

(b)supply the engineer with all such information as the engineer may reasonably require with regard to any relevant work or the method of constructing it.

8.  Network Rail must—

(a)at all times afford reasonable facilities to the undertaker and its agents for access to any works carried out by Network Rail under this Schedule during their construction; and

(b)supply the undertaker with such information as it may reasonably require with regard to such works or the method of constructing them.