SCHEDULE 10Protective provisions
PART 20For the protection of Exolum Pipeline System Ltd
Co-operation and reasonableness
296.
Where Apparatus is required to be protected, altered, diverted or removed under this Schedule, the undertaker must use all reasonable endeavours to co-ordinate the execution of any works under this Schedule—
(a)
in the interests of safety;
(b)
47.2 in the interest of the efficient and economic execution of both Exolum’s works and the Authorised Development; and
(c)
47.3 taking into account the need to ensure the safe and efficient operation of Apparatus and carrying out of Exolum’s functions.