xmlns:atom="http://www.w3.org/2005/Atom"

PART 2PRINCIPAL POWERS

Application of the 1990 Act

6.—(1) This article applies where the Order land is used for the temporary construction works.

(2) Where this article applies, section 57(2) of the 1990 Act (planning permission required for development) applies as if the development consent granted by this Order were planning permission granted for a limited period.

(3) In this article, “the temporary construction works” means works within the proposed multiple purpose construction areas, the proposed soil storage areas, the proposed site compound areas and the proposed borrow land areas as shown on the general arrangement plans.