SCHEDULE 10Protective Provisions

PART 6Protection for East Anglia ONE Offshore Wind Farm and East Anglia THREE Offshore Wind Farm

ExpensesI14

Subject to the following provisions of this paragraph, the undertaker must repay to the statutory undertaker on demand all charges, costs and expenses reasonably and properly incurred by that statutory undertaker in, or in connection with, the inspection, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to herein including without limitation—

a

the approval of plans;

b

the carrying out of protective works, plus a capitalised sum to cover the cost of maintaining and renewing permanent protective works;

c

the survey of apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any such works referred to herein.