The East Anglia TWO Offshore Wind Farm Order 2022

2.  In this part of this schedule—E+W+S

apparatus” means electric lines or electrical plant (as defined in the 1989 Act) belonging to or maintained by the statutory undertaker;

“plan” or “plans” includes all designs, drawings, specifications, method statements, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed;

specified works” means works authorised by this Order (or authorised by any marine licence intended to operate in conjunction with this Order) that are to be carried out within 750 metres of apparatus belonging to a statutory undertaker; and

statutory undertaker” means, as appropriate—

(a)

the statutory undertaker who owns and/or operates the transmission assets under the East Anglia ONE Offshore Wind Farm Order 2014(1);

(b)

the statutory undertaker who owns and/or operates the transmission assets under the East Anglia THREE Offshore Wind Farm Order 2017(2).

Commencement Information

I1Sch. 10 Pt. 6 para. 2 in force at 22.4.2022, see art. 1(2)