SCHEDULE 2REQUIREMENTS

Construction environmental management planI117

1

No part of the authorised development may commence, save for the permitted preliminary works, until a construction environmental management plan for that part has been submitted to and, after consultation with Natural England and the Environment Agency, approved by the relevant planning authority.

2

The plan submitted and approved for that part must be in accordance with the framework construction environment management plan and incorporate—

a

a code of construction practice, specifying measures designed to minimise the impacts of construction works;

b

a scheme for the control of any emissions to air;

c

a soil management plan;

d

a site waste management plan;

e

a sediment control plan;

f

a scheme for environmental monitoring and reporting during the construction of the authorised development, including measures for undertaking any corrective actions;

g

a scheme for the notification of any significant construction impacts on local residents and for handling any complaints received from local residents relating to such impacts during the construction of the authorised development;

h

the contaminated land scheme for that part containing the matters under Requirement 15; and

i

a fish management plan.

3

All construction works associated with the authorised development must be carried out in accordance with the approved construction environmental management plan unless otherwise agreed with the relevant planning authority.