SCHEDULES

SCHEDULE 2REQUIREMENTS

PART 1REQUIREMENTS

Implementation and maintenance of landscaping

6.—(1) All landscaping works must be carried out in accordance with the landscaping scheme approved under requirement 5.

(2) All landscaping works must be carried out to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards or other recognised codes of good practice, and in accordance with the LEMP approved as part of the EMP (construction stage) and EMP (end of construction stage) under requirement 3.

(3) Any tree or shrub planted as part of the landscaping scheme that, within a period of 5 years after planting, is removed, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted.