2021 No. 694
The Offshore Installations (Safety Zones) Order 2021
Made
Coming into force in accordance with article 1(2)
Citation, commencement and extent1
1
This Order may be cited as the Offshore Installations (Safety Zones) Order 2021.
2
This Order comes into force 21 days after the day on which it is made (“the general coming into force date”), except for article 2(1), which comes into force as provided in article 2(2).
3
This Order extends to England and Wales, Scotland and Northern Ireland.
Establishment of safety zones2
1
A safety zone is established around each installation specified in column 1 of the table in the Schedule (being an installation to be stationed in waters to which subsection (7) of section 21 of the Petroleum Act 1987 applies) having a radius of five hundred metres, as respects that installation, from the point which has the co-ordinates of latitude and longitude according to the World Geodetic System 19843 specified in columns 2 and 3 of the table in the Schedule.
2
Paragraph (1) comes into force, as respects each installation specified in the Schedule—
a
on the general coming into force date, where the installation arrives at its station before that date; and
b
when the installation arrives at its station, in any other case.
SCHEDULEInstallations
(1) Name or other designation | (2) Latitude | (3) Longitude |
---|---|---|
22/10a-LAD, Everest, Block 22/10a | 57° 49.910’N | 01° 50.583’E |
Evelyn Wellhead, Evelyn, Block 21/30 | 57⁰ 01.476’N | 00⁰ 50.379’E |
(This note is not part of the Order)