PART 3 E+WPOWERS OF ACQUISITION AND POSSESSION OF LAND

Powers of acquisitionE+W

Modification of the 1965 ActE+W

32.—(1) Part 1 (compulsory purchase under Acquisition of Land Act of 1946) of the 1965 Act, as applied by this Order to section 125 (application of compulsory acquisition provisions) of the 2008 Act is modified as set out in paragraphs (2) to (5).

(2) In section 4A(1) M1 (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order), the three year period mentioned in section 4” substitute “ section 118 (legal challenges relating to applications for orders granting development consent) of the Planning Act 2008, the five year period mentioned in article 25 (time limit for exercise of powers to possess land temporarily or to acquire land compulsorily) of the Lake Lothing (Lowestoft) Third Crossing Order 2020 ”.

(3) In section 11A M2 (powers of entry: further notice of entry)—

(a)in subsection (1)(a) after “land” insert “ under that provision ”; and

(b)in subsection (2) after “land” inset “under that provision”.

(4) In section 22(2) (expiry of time limit for exercise of compulsory purchase power not to affect acquisition of interests omitted from purchase), for “section 4 of this Act” substitute “ article 25 (time limit for exercise of powers to possess land temporarily to acquire land compulsorily) of the Lake Lothing (Lowestoft) Third Crossing Order 2020 ”.

(5) In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)—

(a)for paragraphs 1(2) and 14(2) substitute—

(2) But see article 27(4) (acquisition of subsoil and airspace only) of the Lake Lothing (Lowestoft) Third Crossing Order 2020, which excludes the acquisition of subsoil or airspace only from this Schedule; and

(b)after paragraph 29, insert—

PART 4 E+WINTERPRETATION

30.  In this Schedule, references to entering on and taking possession of land do not include doing so under article 16 (protective works to buildings), 33 (temporary use of land for carrying out the authorised development) or 34 (temporary use of land for maintaining the authorised development) of the Lake Lothing (Lowestoft) Third Crossing Order 2020.

Commencement Information

I1Art. 32 in force at 21.5.2020, see art. 1

Marginal Citations

M1Section 4A was inserted by section 202(1) of the Housing and Planning Act 2016.

M2Section 11A was inserted by section 186(3) of the Housing and Planning Act 2016.