SCHEDULE 4Transitional provisions

Advance notification on or after commencement day

7.—(1) If—

(a)the activities listed in sub-paragraph 3(1)(b) or (c)(i)-(iii) occur on or after commencement day; and

(b)paragraph 7 of this Schedule does not apply

the operator must, unless the ONR has previously agreed in writing to a shorter notice period, make the declaration to the ONR on or after commencement day and not later than 200 days prior to the date on which the activity occurs.

(2) In the case of a new qualifying nuclear facility, which comes into existence on or after 1st January 2021, as described in regulation 7(3), the operator must, unless the ONR has previously agreed in writing to a shorter notice period, send an accountancy and control plan to the ONR no later than 200 days prior to the day on which qualifying nuclear material is first received at the facility.