The components of an accountancy and control system, referred to in regulation 6(3), are set out below:

1)

a structure of material balance areas in which the physical inventory of qualifying nuclear material in each area and the transfers of qualifying nuclear material into and out of each area can be determined. This structure should be designed to maximise the control of qualifying nuclear material flows and physical inventories;

2)

defined roles and responsibilities, that are assigned, and communicated to the staff of a qualifying nuclear facility to meet the obligations contained in these Regulations;

3)

quality assurance and quality control measures that detect, describe, address, and reduce sources of errors in and poor performance of the system;

4)

a programme of measurements that provides accurate, suitably precise, and representative information that quantifies and characterises qualifying nuclear material;

5)

a measurement control programme that validates and provides traceability for measurement results and their uncertainties and ensures that measurements comply with the relevant international standards or are equivalent in quality to those standards, for example by assessing, approving, recording, and calibrating measurement procedures;

6)

the ability to track and document the movement of qualifying nuclear material through receipts, packaging, re-packaging, processing, storage, and shipment in a timely manner. The system should show the location, characteristics, and containment of all qualifying nuclear material;

7)

the ability to unambiguously identify batches of qualifying nuclear material in whatever containers, process vessels, or equipment they may be located in. The locations in which qualifying nuclear material can be held, as well as positions within these areas, should also be identifiable;

8)

an inventory control system to regularly check the agreement between records of qualifying nuclear material, and between those records and the physical reality, and take appropriate action to manage discrepancies as they arise by investigating, documenting, reporting, and resolving such discrepancies;

9)

the ability to manage anomalies consistent with the loss or gain of a significant amount of qualifying nuclear material, or any other situation corresponding with regulation 17 (unusual occurrences), in a timely manner by, for example, recognising, investigating, and documenting such anomalies. The system should define personnel responsibilities and authorities to carry out the actions required by regulation 16 (special reports);

10)

data processing procedures that store, trace, identify, and produce the information required by these Regulations, and that are required to facilitate the checking of data against the physical reality;

11)

reporting and notification procedures that transmit the information required by these Regulations through appropriate channels to the ONR and according to appropriate deadlines;

12)

receipt and shipment procedures that check the quantity and characteristics of qualifying nuclear material entering or leaving a qualifying nuclear facility against the accountancy information that must accompany such receipts and shipments. These procedures should also allow for the introduction or extraction of qualifying nuclear material to or from the tracking, identification, and inventory control processes described above;

13)

a Physical Inventory Taking (PIT), that is carried out in accordance with regulation 15(3) and 31(4)(b) at least every calendar year, with the period between two successive physical inventory takings not exceeding 14 months;

14)

procedures for a PIT that describe the responsibilities of those involved, the methods they should use, the records that should be kept, the associated measurement uncertainties and material balance tests (where appropriate), the reporting that must be made to the ONR, and the steps for authenticating any information made available to inspectors under these Regulations; and

15)

a List of Inventory Items (LII), generated from a PIT, that facilitates inspector verification of information provided to ONR against the physical reality. The LII should include information on the mass and composition of qualifying nuclear material per item, as well as its location, containment, identity, and type.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources