Search Legislation

The A19/A184 Testo’s Junction Alteration Development Consent Order 2018

Status:

This is the original version (as it was originally made).

Archaeological remains

9.—(1) No part of the authorised development is to commence until for that part a written scheme for the investigation of areas of archaeological interest, reflecting the relevant mitigation measures set out in the REAC, has been submitted to and approved in writing by the Secretary of State, following consultation with the relevant planning authority on matters related to its function.

(2) The authorised development must be carried out in accordance with the scheme referred to in sub-paragraph (1).

(3) A copy of any analysis, reporting, publication or archiving required as part of the written scheme referred to in sub-paragraph (1) must be deposited with the Historic Environment Record of the relevant planning authority within one year of the date of completion of the authorised development or such other period as may be agreed in writing by the relevant planning authority or specified in the written scheme referred to in sub-paragraph (1).

(4) Any archaeological remains not previously identified which are revealed when carrying out the authorised development must be retained in situ and reported to the relevant planning authority as soon as reasonably practicable from the date they are identified.

(5) No construction operations are to take place within 10 metres of the remains referred to in sub-paragraph (4) for a period of 14 days from the date of any notice served under sub-paragraph (4) unless otherwise agreed in writing by the relevant planning authority.

(6) If the relevant planning authority determines in writing that the archaeological remains require further investigation, no construction operations are to take place within 10 metres of the remains until provision has been made for the further investigation and recording of the remains in accordance with details to be submitted in writing to, and approved in writing by, the relevant planning authority.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources