PART 8Additional RHI capacity and additional capacity for biomethane production

Additional capacity for biomethane production77

1

A participant—

a

who is a producer of biomethane for injection;

b

whose original application for registration was made on or after 28th May 2014; and

c

who is producing additional biomethane for injection,

may apply to the Authority to be registered in respect of that additional biomethane.

2

Regulation 32(2) to (8), (10)(a) to (c) and (e), and (11) to (14) applies to an application for registration in respect of additional biomethane, but as if—

a

references to an applicant were references to the participant,

b

references to biomethane were references to additional biomethane,

c

references to registering the applicant as a participant were references to registering the participant in respect of that additional biomethane.

3

Where a participant is registered in respect of additional biomethane, the Authority must specify the maximum additional capacity in relation to which the participant is being registered.

4

Periodic support payments for additional biomethane may not be made beyond the tariff end date notified in accordance with regulation 32(10)(d) when the participant was originally registered as a producer of biomethane for injection.

5

For the purposes of this regulation—

a

“additional biomethane” means any biomethane—

i

which exceeds the sum of the maximum initial capacity, together with any maximum additional capacity previously specified under this regulation; and

ii

which is being supplied by the participant for injection at the same injection point as the biomethane in respect of which that participant was first registered;

b

“maximum additional capacity” means the volume of biomethane expressed in cubic metres per quarterly period which—

i

is additional biomethane; and

ii

is the maximum volume which a participant is entitled to supply for injection under the network entry agreement applicable to that additional biomethane.

6

Where the Authority does not register an applicant in respect of additional biomethane, it must notify the applicant in writing that the application for registration has been rejected, giving reasons.