SCHEDULES

SCHEDULE 13PROTECTIVE PROVISIONS

PART 3FOR THE PROTECTION OF NATIONAL GRID

Acquisition of land

20.—(1) This Order does not authorise the acquisition or extinguishment of land or rights in land or override any interest in land owned by National Grid that is required for the retention or maintenance of any retained apparatus except with National Grid’s agreement (such agreement not to be unreasonably withheld or delayed).

(2) As a condition of agreement between the parties in sub-paragraph (1), prior to the carrying out of any part of the authorised development (or in such other timeframe as may be agreed between National Grid and TfL) that are subject to the requirements of this Part of this Schedule that will cause any conflict with or breach the terms of any easement or other legal or land interest of National Grid or affects the provisions of any enactment or agreement regulating the relations between National Grid and TfL in respect of any apparatus laid or erected in land belonging to or secured by TfL, TfL must as National Grid reasonably requires enter into such deeds of easement or consent upon such terms and conditions as may be agreed between National Grid and TfL acting reasonably and which must be no less favourable on the whole to National Grid unless otherwise agreed by National Grid, and it is the responsibility of TfL to procure or secure the consent and entering into of such deeds and variations by all other third parties with an interest in the land at that time who are affected by such authorised development.

(3) Where there is any inconsistency or duplication between the provisions set out in this Part of this Schedule relating to the relocation or removal of apparatus (including but not limited to the payment of costs and expenses relating to such relocation or removal of apparatus) and the provisions of any existing easement, rights, agreements and licences granted, used, enjoyed or exercised by National Grid or other enactments relied upon by National Grid as of right or other use in relation to the apparatus, then the provisions in this Part of this Schedule prevail.

(4) No agreement or consent granted by National Grid under any other provision of this Part of this Schedule constitutes agreement under sub-paragraph (1).