The Hornsea Two Offshore Wind Farm (Amendment) (No. 2) Order 2018

Citation and commencement

1.  This Order may be cited as the Hornsea Two Offshore Wind Farm (Amendment) (No. 2) Order 2018 and comes into force on 8th May 2018.

Amendment to the Hornsea Two Offshore Wind Farm Order 2016

2.—(1) The Hornsea Two Offshore Wind Farm Order 2016 is amended as follows.

(2) In paragraph 3(1) of Part 1 (Authorised Development) of Schedule 1 (Authorised Project), in the descriptions of Work No. 2A and Work No. 2B, for “up to 6 offshore HVAC collector substations”, where it occurs, substitute “up to 3 offshore HVAC collector substations”.

(3) In paragraph 3(2) of Part 1 (Authorised Development) of Schedule 1 (Authorised Project), for “must not exceed 6” substitute “must not exceed 3”.

(4) In paragraph 2(4)(b) of Part 3 (Requirements) of Schedule 1 (Authorised project), for “3,600 square metres in area or 60 metres in width” substitute “6,300 square metres in area or 90 metres in width”.

Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy

Gareth Leigh

Head of Energy Infrastructure Planning

Department for Business, Energy and Industrial Strategy

4th May 2018