The Hinkley Point C (Nuclear Generating Station) (Amendment) Order 2018

Amendment to Part 1 (Authorised development) of Schedule 1 (Authorised project)

3.—(1) In Part 1 of Schedule 1 to the Order the description of Work No. 1A is amended as follows:

(2) In paragraph (d)(i)—

(a)after “Effluent Tanks” insert “and Refuelling Water Storage Tank”;

(b)after “Battery Load Bank;” insert “and”;

(c)after “Cooling Water Discharge Weir (Buildings)” omit “and Refuelling Water Storage Tank;”.

(3) In paragraph (h)—

(a)after “Service Access Buildings;” omit “and”;

(b)in the list below “Service Access Buildings;”, insert “Underground Tunnel High Points;”; and

(c)in the list, below “Services Ventilation Building;” insert—

Back Up Containerised Generators; and

Valve Room for Demineralisation Station.