18. In Schedule 2, in the notice, in the last box beginning with the word “Insert”, for paragraph (e) substitute—
“(e)date giving a period (as the case may be) of—
(i)14 days beginning with the date when the notice is published in a newspaper under article 13; or
(ii)21 days beginning with the date when the notice is first displayed on or near the site or served on an owner/occupier of adjoining land under article 14; or
(iii)21 days beginning with the date the notice is served on an infrastructure manager under article 14A; or
(iv)30 days beginning with the date the notice is published, displayed or served in relation to an EIA application accompanied by an environmental statement;
and when computing the number of days in sub-paragraphs (i) and (ii), any day which is a public holiday must be disregarded.”.