PART 6 U.K.Notification of completed measures

Notification requirements for completed measuresU.K.

24.—(1) A measure is notified to the Administrator in accordance with this article if the notification—

(a)is made, in writing, by the participant that promoted the measure;

(b)includes a calculation of the score for the measure;

(c)if the measure is a demonstration action, includes—

(i)the total cost in pounds sterling incurred by the participant in promoting and monitoring the demonstration action (“the actual cost”);

(ii)a breakdown of the actual cost;

(iii)the information obtained by the participant as to whether the demonstration action achieved cost savings; and

(iv)an assessment of the effectiveness of the demonstration action at achieving cost savings;

(d)includes such other information relating to the measure as the Administrator may require;

(e)is made after the measure is completed; and

(f)is made on time within the meaning of article 25.

(2) The Administrator must publish, on its website, a summary of the information provided by a participant in respect of a demonstration action under paragraph (1)(c).

(3) For the purposes of this Order, a measure is completed—

(a)in the case of a demonstration action, when the planned monitoring of the demonstration action is completed;

(b)in any other case, when the installation of the measure is completed.

(4) In this article, “planned monitoring” means the arrangements for monitoring whether a demonstration action achieves cost savings—

(a)as described in the application for approval of the demonstration action in accordance with article 20(2)(a)(iii); or

(b)as otherwise agreed, in writing, by the Administrator.