INFRASTRUCTURE PLANNING
This Order grants development consent for, and authorises East Anglia THREE Limited to construct, operate and maintain a generating station located in the North Sea approximately 69 kilometres from the coast at Lowestoft, together with all necessary and associated development. For the purposes of the development that it authorises East Anglia THREE Limited is authorised by the Order compulsorily or by agreement to purchase land and rights in land to use land, as well as to override easements and other rights. The Order also provides a defence in proceedings in respect of statutory nuisance and to discharge water. The Order imposes requirements in connection with the development for which it grants development consent.
The East Anglia THREE Offshore Wind Farm Order 2017
art. 23(1)(t)
The East Anglia THREE Offshore Wind Farm (Correction) Order 2018
Sch.
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 1
para. 1
The East Anglia THREE Offshore Wind Farm (Correction) Order 2018
Sch.
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 2(1)(a)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(a)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 2(1)(c)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(b)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 2(1)(e)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(c)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 2(2)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(d)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 2(3)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(e)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 3(1)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(f)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 3(2)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(g)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 3(8)(a)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(h)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 3(8)(e)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(i)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 7(2)(a)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(j)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 7(2)(b)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(k)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 7(2)(c)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(l)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 8(2)(a)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(m)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 33
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021
art. 6(n)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 2(1)(a)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022
art. 4(a)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 2(1)(c)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022
art. 4(b)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 3(8)(a)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022
art. 4(c)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 3(8)(a)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022
art. 4(c)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 33(1)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022
art. 4(d)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 33(2)(a)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022
art. 4(e)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 33(2)(c)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022
art. 4(f)
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 1
para. 38
The East Anglia THREE Offshore Wind Farm (Amendment) (No. 2) Order 2022
art. 2
art. 1
The East Anglia THREE Offshore Wind Farm Order 2017
Sch. 1 Pt. 3
para. 3(9)
The East Anglia THREE Offshore Wind Farm (Amendment) Order 2019
art. 4(2)
art. 1
SCHEDULES
SCHEDULE 8Protective Provisions
PART 7Protection for oil and gas licensees
Proximity Agreement78