SCHEDULE 8Protective Provisions

PART 5Protection for National Grid as electricity and gas undertaker and National Grid Gas Distribution Limited as gas undertaker

Co-operation

59.—(1) Where in consequence of the proposed construction of any of the authorised works, the undertaker or a statutory undertaker requires the removal of apparatus under paragraph 52(2) or a statutory undertaker makes requirements for the protection or alteration of apparatus under paragraphs54 and 55, the undertaker must use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of the statutory undertaker’s undertaking and each statutory undertaker must use its best endeavours to co-operate with the undertaker for that purpose.

(2) For the avoidance of doubt whenever the statutory undertaker’s consent, agreement or approval to is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by the undertaker, it must not be unreasonably withheld or delayed.