SCHEDULES

SCHEDULE 1Authorised project

PART 3Requirements

Ecological management plan21

1

No stage of the connection works may commence until for that stage a written ecological management plan (which accords with the outline landscape and ecological management strategy) reflecting the survey results and ecological mitigation and enhancement measures included in the environmental statement has been submitted to and approved by the relevant planning authority in consultation with Natural England.

2

The ecological management plan must include an implementation timetable and must be carried out as approved.

3

Construction works between Ferry Road and the River Deben must be carried out in accordance with the embedded mitigation relating to onshore ornithology contained in Table 2 of the outline landscape and ecological management strategy, which must be incorporated into the ecological management plan.