PART 3ACQUISITION AND POSSESSION OF LAND

Temporary possession or use of land

Temporary use of land for construction of works9

1

Network Rail may in connection with the carrying out of the authorised works enter upon and take temporary possession of the land within the Order limits for the purposes of provision of a worksite and access and construction of the authorised works on that land.

2

Not less than 14 days before entering upon and taking temporary possession of land under this article Network Rail must serve notice of the intended entry on the owners and occupiers of the land.

3

Network Rail may not, without the agreement of the owners of the land, remain in possession of any land under this article after the end of the period of one year beginning with the date of completion of the authorised works for the purposes of which temporary possession of that land was taken.

4

Before giving up possession of land of which temporary possession has been taken under this article, Network Rail must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but Network Rail is not required to replace a building removed in connection with the carrying out of the authorised works or restore the land on which any permanent works have been constructed under paragraph (1).

5

Network Rail must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.

6

Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount of the compensation, is to be determined under Part 1 of the 1961 Act.

7

Without affecting article 14 (no double recovery), nothing in this article affects any liability to pay compensation under section 10(2)14 (further provision as to compensation for injurious affection) of the 1965 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (5).

8

Where Network Rail takes possession of land under this article, it is not required to acquire the land or any interest in it.

9

Section 1315 (refusal to give possession to the acquiring authority) of the 1965 Act applies to the temporary use of land under this article.