70.—(1) The assessment provisions apply in relation to—

(a)granting planning permission on an application under Part 3 of the TCPA 1990 (control over development);

(b)granting planning permission on an application under section 293A of that Act (urgent Crown development)(1);

(c)granting planning permission, or upholding a decision of the local planning authority to grant planning permission (whether or not subject to the same conditions and limitations as those imposed by the local planning authority), on determining an appeal under section 78 of that Act (right to appeal against planning decisions)(2) in respect of such an application;

(d)granting planning permission under—

(i)section 141(2)(a) of that Act (action in relation to purchase notice); or

(ii)section 177(1)(a) of that Act (grant or modification of planning permission on appeals against enforcement notices)(3);

(e)directing under the following provisions that planning permission is deemed to be granted—

(i)section 90(1), (2) or (2A) of that Act (development with government authorisation);

(ii)section 57(2) or (2A) of the Town and Country Planning (Scotland) Act 1997 (development with government authorisation)(4); or

(iii)section 5(1) of the Pipe-lines Act 1962 (provisions with respect to planning permission concerning pipe-lines)(5);

(f)directing under section 90(2ZA)(a) or (b) of the TCPA 1990(6) or section 57(2ZA)(a) or (b) of the Town and Country Planning (Scotland) Act 1997(7), in respect of a planning permission which is deemed to be granted under section 90(2) or section 57(2) (respectively) on varying a consent under section 36 or 37 of the Electricity Act 1989(8), that that permission, or any conditions subject to which it was granted, be varied;

(g)making—

(i)an order under section 102 of the TCPA 1990 (orders requiring discontinuance of use or alteration or removal of buildings or works)(9), including an order made under that section by virtue of section 104 of that Act (powers in relation to section 102 orders) which grants planning permission, or confirming any such order under section 103 of that Act (confirmation of section 102 orders); or

(ii)an order under paragraph 1 of Schedule 9 to that Act (order requiring discontinuance of mineral working)(10), including an order made under that paragraph by virtue of paragraph 11 of that Schedule (powers in relation to orders under Schedule 9) which grants planning permission; or

(h)directing under the following provisions that, if an application is made for planning permission, it must be granted—

(i)section 141(3) of the TCPA 1990 (action in relation to purchase notice); or

(ii)section 35(5) of the Planning (Listed Buildings and Conservation Areas) Act 1990 (action in relation to listed building purchase notice)(11).

(2) Where the assessment provisions apply, the competent authority may, if it considers that any adverse effects of the plan or project on the integrity of a European site or a European offshore marine site would be avoided if the planning permission were subject to conditions or limitations, grant planning permission, or, as the case may be, take action which results in planning permission being granted or deemed to be granted, subject to those conditions or limitations.

(3) Where the assessment provisions apply, outline planning permission must not be granted unless the competent authority is satisfied (whether by reason of the conditions and limitations to which the outline planning permission is to be made subject, or otherwise) that no development likely adversely to affect the integrity of a European site or a European offshore marine site could be carried out under the permission, whether before or after obtaining approval of any reserved matters.

(4) In paragraph (3), “outline planning permission” and “reserved matters” have the same meanings as in section 92 of the TCPA 1990 (outline planning permission)(12).

(1)

Section 293A was inserted by the Planning and Compulsory Purchase Act 2004 (c. 5), section 82(1), and amended by the Planning (Wales) Act 2015 (anaw 4), Schedule 2, paragraphs 8 and 9, and Schedule 4, paragraphs 1 and 17; and the Housing and Planning Act 2016 (c. 22), Schedule 12, paragraph 34.

(2)

Section 78 was amended by the Planning and Compensation Act 1991 (c. 34), section 17(2); the Planning and Compulsory Purchase Act 2004, sections 40(2)(e) and 43(2); the Planning Act 2008 (c. 29), Schedule 10, paragraphs 1 and 3 and Schedule 11, paragraphs 1 and 2; the Localism Act 2011 (c. 20), section 123(1) and (3), and Schedule 12, paragraphs 1 and 11; the Growth and Infrastructure Act 2013 (c. 27), Schedule 1, paragraphs 1 and 8; the Infrastructure Act 2015 (c. 7), Schedule 4, Part 2, paragraphs 2 and 12; the Planning (Wales) Act 2015, sections 45 and 47, and Schedule 7, paragraph 7; the Housing and Planning Act 2016, Schedule 12, paragraphs 1 and 21; and by S.I. 2014/2773.

(3)

Section 177(1)(a) was substituted by the Planning and Compensation Act 1991, Schedule 7, paragraph 24(1)(a).

(4)

1997 c. 8. Section 57(2) was substituted by the Growth and Infrastructure Act 2013 (c. 27), section 21(5).

(5)

1962 c. 58. Section 5(1) was amended by S.I. 1999/742.

(6)

Section 90(2ZA) was inserted by the Environment Act 1995 (c. 25), Schedule 10.

(7)

Section 57(2ZA) was inserted by the Growth and Infrastructure Act 2013 (c. 27), section 21(5).

(8)

1989 c. 29. Section 36 was amended by the Energy Act 2004 (c. 20), section 93; by the Planning Act 2008, Schedule 2, paragraphs 31 and 32; by the Marine Act, section 12(7)(a) and (8); by the Energy Act 2016 (c .20), section 78; and by S.I. 2006/1054; and is prospectively amended by the Wales Act 2017 (c. 4), section 39(7) to (11), and Schedule 6, Part 3, paragraph 47, from a date to be appointed. Section 36C of the Act, inserted by the Growth and Infrastructure Act 2013 (c. 27), section 20, provides for the variation of consents granted under section 36. Section 37 was amended by the Planning Act 2008, Schedule 2, paragraphs 31 and 33; and is prospectively amended by the Wales Act 2017, section 42 from a date to be appointed.

(9)

Section 102 was amended by the Planning and Compensation Act 1991 (c. 34), Schedule 1, paragraph 6, and Schedule 7, paragraph 21; and the Planning (Wales) Act 2015 (anaw 4), section 33(1) and (4).

(10)

Paragraph 1 of Schedule 9 was amended by the Planning and Compensation Act 1991, Schedule 1, paragraph 15.

(11)

1990 c. 9.

(12)

Section 92 was amended by the Planning (Wales) Act 2015 (anaw 4), section 36(1) to (6), and Schedule 4, paragraphs 1 and 10.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources