The Brechfa Forest Wind Farm Connection Order 2016

Applications made under Requirement

1.  Where an application has been made to the relevant planning authority for any agreement or approval required pursuant to a Requirement included in this Order, the relevant planning authority must give notice to the undertaker of their decision including the reasons on the application, within a period of 8 weeks beginning with—

(a)the day immediately following that on which the application is received by the authority; or

(b)such longer period as may be agreed by the undertaker and the relevant planning authority.