Pre-construction monitoring and surveys

12.—(1) The undertaker must submit details for written approval by the MMO after consultation with the statutory nature conservation body of—

(a)proposed pre-construction surveys including methodologies and timings; and

(b)a proposed format and content for a pre-construction baseline report.

(2) The survey proposals must specify the objectives of each survey and explain how the survey will assist in either informing a useful and valid comparison with the post-construction position and/or will enable the validation or otherwise of key predictions in the environmental statement.

(3) The baseline report proposals must ensure that the outcome of the agreed surveys together with existing data and reports are drawn together to present a valid statement of the pre-construction position, with any limitations, and must make clear what post-construction comparison is intended and the justification for this being required.

(4) The pre-construction surveys referred to in paragraph (1) must, unless otherwise agreed with the MMO, have due regard to, but not be limited to, the need to undertake—

(a)appropriate surveys to determine the location, extent and composition of any Annex 1 habitat biogenic reef features (Mytilus edulis and/or Sabellaria spinulosa) within the Inner Dowsing, Race Bank and North Ridge Site of Community Importance or biogenic reef features in whole or in part inside the areas within the offshore Order limits in which it is proposed to carry out construction works;

(b)swath bathymetric surveys, to International Hydrographic Organization Order IA standard, and side-scan sonar surveys of the areas within the offshore Order limits in which it is proposed to carry out construction works, the data and survey reports to be provided to the UKHO; and

(c)1 high-resolution bathymetric and side-scan sonar survey of the areas within the offshore Order limits in which it is proposed to carry out construction works including a 500-metre buffer area around the site of each works. This should include the identification of sites of historic or archaeological interest in accordance with the written scheme of archaeological investigation.

(5) The undertaker must carry out the surveys agreed under paragraph (1) and provide the baseline report to the MMO in the agreed format in accordance with the agreed timetable, unless otherwise agreed in writing by the MMO after consultation with the statutory nature conservation body.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made):The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources