The Hornsea Two Offshore Wind Farm Order 2016

8.—(1) Where, in exercise of the powers conferred by this Order,—

(a)the relevant undertaker acquires any interest in any land in which apparatus is placed; and

(b)the apparatus is to be relocated, extended, removed or altered in any way,

no alteration or extension may take place until Anglian Water has established, to its reasonable satisfaction, contingency arrangements in order to conduct its functions for the duration of the works to relocate, extend, remove or alter the apparatus.

(2) Anglian Water must use reasonable endeavours to establish contingency arrangements in a timely manner.